miércoles, 10 de septiembre de 2008

DFBs in 12-23-34-56-67-78-81 Sectors 18:44:32 hs.


The temperature of the sector reached its nominal value. During the last week the re-commissioning of the superconducting circuit started and almost ended: few tests of the inner-triplet circuit (low beta magnets) are missing. The tests involving group of circuits of the arc and the matching sections were started in the end of the past week. The sector is ready for the injection day.



During the last two weeks, the repair of the broken turbine at point 6 was performed, together with some other installation activities, mainly the mounting of the shielding in front of the RR73.

adolfocanals@educ.ar

No hay comentarios: