The sector is commissioned and ready for the beam injection
The cryogenics conditions of the sector are stable at 1.9K. The sector is ready for the injection day. The last test to verify the global protection mechanism and the possible electro-magnetic coupling are ongoing. The cooling issue of the circuits of the DFBLC has been identified in the first part of the cryo-link; the problem will be fixed after the 10th September. Dedicated tests were carried out on the circuits powered via this DFB and it has been verified that the current level needed for the injection day is allowed and not harmful. All the other circuits belonging to the sector are fully commissioned.